avancrea logo
Measuring the right decisions
“EVTA: Earn Value Technique Analysis”: Sistema de control de coste basado en el valor aportado al avance del proyecto. Descripción de los Términos e interpretación de Earned Value Management 1. PV (BCWS)  Planned Value: estimated value of the workplanned to be done. 2. EV (BCWP)  Earned Value: estimated value of the work accomplished. 3. AC (ACWP)  Actual Cost: actual cost incurred. 4. BAC  Budget at Completion: How much did you BUDGET for the TOTAL JOB? 5. EAC  Estimate at Completion: current expected cost of the TOTAL project. 6. ETC  Estimate to Complete: From this point on, how much MORE do we expect it to cost to finish the job? 7. VAC  Variance at Completion: How much over or under budget do we expect to be?
Fórmulas: 1. Cost Variance (CV)  EV – AC  NEGATIVE is over budget, POSITIVE is under budget 2. Schedule Variance (SV)  EV – PV NEGATIVE is behind schedule, POSITIVE is ahead of schedule 3. Cost Performance Index (CPI) EV / AC  I am [only] getting _____ cents out of every $1. 4. Schedule Performance Index (SPI) EV / PV  I am [only] progressing at ___% of the rate originally planned. 5. Estimate At Completion (EAC) Note: There are many ways to calculate EAC. 1. BAC / CPI • Used if no variances from the BAC have occurred 2. AC + ETC • Actual plus a new estimate forremaining work. Used when original estimate was fundamentally flawed.
...
Al visitar esta página web acepta que podamos instalar cookies en su dispositivo. Vea nuestra política de cookies en Aviso Legal para ampliar la información.

Metodologías Excelencia

avancrea logo

Metodologías Excelencia

“EVTA: Earn Value Technique Analysis”: Sistema de control de coste basado en el valor aportado al avance del proyecto. Descripción de los Términos e interpretación de Earned Value Management 1. PV (BCWS)  Planned Value: estimated value of the workplanned to be done. 2. EV (BCWP)  Earned Value: estimated value of the work accomplished. 3. AC (ACWP)  Actual Cost: actual cost incurred. 4. BAC  Budget at Completion: How much did you BUDGET for the TOTAL JOB? 5. EAC  Estimate at Completion: current expected cost of the TOTAL project. 6. ETC  Estimate to Complete: From this point on, how much MORE do we expect it to cost to finish the job? 7. VAC  Variance at Completion: How much over or under budget do we expect to be?
Fórmulas: 1. Cost Variance (CV)  EV – AC  NEGATIVE is over budget, POSITIVE is under budget 2. Schedule Variance (SV)  EV – PV NEGATIVE is behind schedule, POSITIVE is ahead of schedule 3. Cost Performance Index (CPI) EV / AC  I am [only] getting _____ cents out of every $1. 4. Schedule Performance Index (SPI) EV / PV  I am [only] progressing at ___% of the rate originally planned. 5. Estimate At Completion (EAC) Note: There are many ways to calculate EAC. 1. BAC / CPI • Used if no variances from the BAC have occurred 2. AC + ETC • Actual plus a new estimate forremaining work. Used when original estimate was fundamentally flawed.
...
Measuring the right decisions